Lindenhurst Building Permit: A Violation Can Follow the House

November 2, 2026, updated · John Tiburzi, Licensed Real Estate Salesperson

A Village building violation on a Lindenhurst home does not end when the deed changes hands. Section 193-137 F of the Village Code says a judgment in a Village action over a code violation becomes a lien on the premises from the day a notice of lis pendens is filed in the Suffolk County Clerk's office, and that the lien can be enforced against the property even if it is transferred after that filing.

Section 193-137 G goes further. The Building Inspector may file that notice any time after serving a violation notice, including when he is satisfied the owner is about to transfer the property to avoid responsibility for the violation. For a seller, a served violation notice is a closing problem from the day it arrives, not something a buyer quietly inherits. For a buyer, the part that matters is whether a notice has been served at all, because a lis pendens filed after that point attaches to the house, not to the seller.

The Lindenhurst houses this applies to

Of the eight Lindenhurst houses I have sold, all on the seller side between 2021 and 2025, five were built before 1960 and none after 1972. Every one was more than fifty years old on the day it sold. A certificate of occupancy issued when a house like that was new can predate half a century of decks, sheds, finished basements and converted garages added by later owners. On a Lindenhurst listing I pull the Village certificate of occupancy and compare it with what is standing on the lot before the photographs are taken.

The full pre-listing sequence is in the sellers guide.

What the Village title search shows

The Building Department's Building Permits page says a certificate of occupancy search starts with a request form sent to the Building Department by email. That form, the Village's Title Search Request Form dated September 3, 2020, asks for the property address and the Suffolk County tax map number, which in the Village begins 0103, and offers four searches:

  • an official certificate of occupancy and violation search
  • a violation search only
  • verification of attached documents only
  • a vacant land check only

The form says a fee may apply based on the results: $75 when an official certificate of occupancy is issued and $25 for any of the official letters. It also warns that checking more than one box may lead to a request to resubmit or slow the results.

The combined certificate and violation search is the one that carries weight at a sale, because it answers both questions a buyer's attorney asks in a single Village reply: what the house is approved as, and whether anything is open against it. A seller who orders it before listing sees the same answer the buyer's title company sees later, while there is still time to act on it.

For the full file, the Village's Online Forms page lists a Freedom of Information request form and says Building Department files are not sent by email; they can be reviewed in person at Village Hall, 430 South Wellwood Avenue.

How a CO for an existing house depends on the violation file

Under Section 193-131 C of the Village Code, the lawful use of an existing structure may continue, and on the owner's written request the Building Inspector issues a certificate of occupancy for it after an inspection, provided no notices of violation or other notices or orders are pending in the Building Inspector's department. Section 193-131 G says a certificate is issued within 10 days after written application if the structure is entitled to it, and that copies are furnished, for a fee, to any person with a proprietary interest in the structure.

Read together, those two lines set the order of work. A pending violation stops the certificate, so the violation is cleared first and the certificate requested second. The 10 day line is the part a seller can plan around; the inspection and any open notice are the parts that cannot be scheduled.

When finished work still counts as open

Section 193-131 B covers alterations. If a house stays occupied while the work goes on, occupancy may not continue for more than 30 days after the alteration is finished unless a certificate of occupancy has been issued for it. A renovation that was permitted, built and lived in, but never inspected to a certificate, is still an open item on the Village file. For a buyer, a permit on file is not the same thing as a certificate on file, and the title search shows which one the house has.

Section 193-129 sets the boundary on the other side. Ordinary repairs need no notice to the Building Inspector, but that exemption does not cover cutting away any wall or part of one, removing or cutting beams or supports, removing, changing or closing a stairway or required exit, or altering a house sewer or drainage system. An opened kitchen wall or a moved staircase is permit work under that section even when nothing was added to the footprint.

Legalizing existing work before listing

The Village posted a revised building permit application in August 2026, and its requirement list covers work that is already built. For legalization of existing work other than internal work, such as a garage conversion, the survey has to show the location and dimensions of that work. The plans requirement applies to proposed or existing structures. An electrical certificate is required if electrical work "is being done or has been done", so wiring inside a finished basement belongs in the legalization file, not only new wiring. Elevation data is required for accessory structures such as a garage or shed, and every new structure in a flood zone needs an elevation certificate from a surveyor before a certificate of occupancy issues.

For a seller, the electrical line carries the weight in that list. A basement or garage conversion finished years ago may need its wiring inspected by one of the electrical inspection agencies the Village lists, because the application says no certificate of occupancy will be issued without an electrical certificate and plumbing approval.

Related: Lindenhurst second floor additions and Lindenhurst flood zones.

What to do before listing, in order

  1. Find the Suffolk County tax map number for the house; inside the Village it begins 0103.
  2. Send the Village Title Search Request Form to the Building Department with one box checked: the official certificate of occupancy and violation search.
  3. Walk the house and lot with the result in hand and list everything standing that the certificate does not cover, including any opened wall or moved stair.
  4. If a violation comes back, clear it first, since Section 193-131 C ties a certificate for an existing structure to there being no pending notice.
  5. For each item to legalize, gather a survey showing the work, plans of the existing structure and an electrical certificate for any wiring, then file the August 2026 building permit application.
  6. After the final inspection, apply in writing for the certificate of occupancy, which Section 193-131 G says issues within 10 days if the structure is entitled to it.
  7. Keep the new certificate and the Village search letter together for the buyer's attorney.

The offer steps: buyers guide.

Thinking of selling? Read the Lindenhurst Seller’s Guide

Questions about Lindenhurst

Do you need a permit for a fence in Lindenhurst?

Inside the Incorporated Village of Lindenhurst, Section 193-132 G of the Village Code says building or altering a fence in a residential zone does not need a building permit, provided the fence otherwise complies with the code. Section 193-132 A lists a separate fee for fences that require a zoning variance, so a fence outside the code's limits goes through that process instead.

Do I need a permit for a shed in the Village of Lindenhurst?

Not for one small shed. Section 193-132 E of the Lindenhurst Village Code exempts one shed of no more than 100 square feet and eight feet high in a residential zone, if it sits behind the rear house line or 45 feet or more from the front property line, and two feet or more from the rear and side lines. A larger or second shed needs a permit.

Do you need a permit for a deck in Lindenhurst?

In the Village of Lindenhurst, Section 193-132 F of the Village Code says a deck less than 18 inches high needs no building permit in a residential zone, provided it otherwise complies with the code. A deck 18 inches or higher is permit work, and the Village's building permit application asks for a survey showing where it sits and its dimensions.

How long is a building permit good for in Lindenhurst?

Section 193-130 D of the Lindenhurst Village Code says a permit expires if no work starts within one year of issue, and every permit expires two years from the date of issue unless the work is completed and approved by the Building Inspector before then. An expired permit with unfinished or uninspected work is an open item when the house is sold.

What happens if you build without a permit in Lindenhurst?

Section 193-132 D of the Lindenhurst Village Code, last amended December 1, 2009, increases every fee by 200 percent when work starts before the permit is issued. Section 193-139, last amended December 2, 2014, sets a fine of not less than $250 for each offense, and the owner, the contractor and anyone else who assisted are each guilty of a separate offense.

Can a homeowner get a building permit in Lindenhurst?

Yes. Section 193-123 of the Lindenhurst Village Code has the owner or lessee file the application, with a sworn statement naming each owner of the property. When someone other than the owner does the work, Section 193-124 calls for a sworn statement that the person is authorized. The Village's Online Forms page lists a workers' compensation exemption affidavit for an owner-occupied one to four family residence.

Sources

  1. https://villageoflindenhurstny.gov/planning-board-business-meeting/building-department/building-permits/
  2. https://villageoflindenhurstny.gov/wp-content/uploads/2026/08/Building-Permit.pdf
  3. https://villageoflindenhurstny.gov/wp-content/uploads/2020/09/Title-Search-Request-Form-Sept-3-2020.pdf
  4. https://villageoflindenhurstny.gov/resources/online-forms/
  5. https://ecode360.com/5119247

More about Lindenhurst

Get market updates from John

John will send occasional updates. You can stop them any time.

Privacy

John Tiburzi Talk to John